If 2 men and 3 women can do a piece of work in 8 days, and 3 men and 2 women can do it in 7 days, how many days will 5 men and 4 women take together?
- A3 days
- B4 days
- C5 days
- DMore than one of the above
- ENone of the above
Show answer and explanation
Correct answer: (b) 4 days
Explanation
8(2m + 3w) = 7(3m + 2w) gives 16m + 24w = 21m + 14w, so 5m = 10w and one man equals two women. The work is 8 × (4 + 3) = 56 woman-days. 5 men and 4 women equal 14 women, who take 56 ÷ 14 = 4 days.