A can complete a piece of work in 15 days and B in 8 days, while B and C together can complete it in 4 days. If A and C together take x days and A and B together take y days, what is x/y?
- A1
- B1½
- C1/2
- DMore than one of the above
- ENone of the above
Show answer and explanation
Correct answer: (a) 1
Explanation
C does 1/4 − 1/8 = 1/8 a day, the same as B. So A + C and A + B each do 1/15 + 1/8 = 23/120 a day, and x = y. Hence x/y = 1.