General Mental Ability & Aptitude PYQ 140 of 391 · Time and Work

A can complete a piece of work in 15 days and B in 8 days, while B and C together can complete it in 4 days. If A and C together take x days and A and B together take y days, what is x/y?

  1. A1
  2. B1½
  3. C1/2
  4. DMore than one of the above
  5. ENone of the above

BPSC TRE-3 (Jul 2024)

Show answer and explanation

Correct answer: (a) 1

Explanation

C does 1/4 − 1/8 = 1/8 a day, the same as B. So A + C and A + B each do 1/15 + 1/8 = 23/120 a day, and x = y. Hence x/y = 1.