Home

Geography PYQ 701 of 2611 · Irrigation, Canals & River Valley Projects

Which one of the following pairs is not correctly matched regarding peculiarities of Ramganga project?

  1. ADam's length - 825.8 metres
  2. BHydropower - 198 MW generation capacity
  3. CLocation - Garhwal (Uttarakhand)
  4. DIrrigated area - 6 lac hectares

UPPSC Prelims 2024

Show answer and explanation

Correct answer: (a) Dam's length - 825.8 metres

Explanation

Under the Ramganga Project, the Ramganga (Kalagarh) Dam was built near Kalagarh in Pauri Garhwal district of Uttarakhand. It is about 128 m high and about 715 m long, so (a)'s 825.8 m is wrong. Its power capacity is 198 MW (3 × 66 MW). By Volume 1 of the Central Water Commission's Ramganga report of February 2012, the project aimed to bring an extra 5.90 lakh ha under irrigation, close to 6.0 lakh ha, though some government sources put the area it irrigates at only 57,500 ha. The UPPSC's preliminary answer key gave (a).

Practise this questionAll 2611 Geography PYQs