Which of the following nuclear power plants has the highest total installed capacity?
- AKakrapar
- BKaiga
- CKudankulam
- DTarapur
Show answer and explanation
Correct answer: (c) Kudankulam
Explanation
The Tarapur atomic power plant in Maharashtra has a total installed capacity of 1400 MW, and Kaiga of 880 MW. Kakrapar has 1840 MW, counting its latest 700 MWe unit, which began commercial operation on 31 March 2024. As of 31 January 2026, Kudankulam has the highest total installed capacity, 2000 MW.