Arrange the following thermal power projects of India from east to west: 1. Kota 2. Namrup 3. Obra 4. Parichha Choose the correct answer using the code given below:

  1. A1, 2, 3, 4
  2. B2, 4, 1, 3
  3. C2, 3, 4, 1
  4. DMore than one of the above
  5. ENone of the above

B.P.S.C. (11-12th) 26.08.2023

Show answer and explanation

Correct answer: (c) 2, 3, 4, 1

Explanation

The correct east-to-west sequence of the given thermal power projects is: Namrup (Assam) – Obra (Sonbhadra, Uttar Pradesh) – Parichha (Jhansi, Uttar Pradesh) – Kota (Rajasthan).