If 10 workers can dig a well in 4 days, how many workers are needed to dig the same well in half a day?

  1. A5
  2. B40
  3. C60
  4. D80

40th BPSC Prelims 1995

Show answer and explanation

Correct answer: (d) 80

Explanation

The work is 10 × 4 = 40 worker-days. To do it in ½ day needs 40 ÷ ½ = 80 workers.