Consider the following pairs:
| Programme/Project | Ministry |
|---|---|
| 1. Drought-Prone Area Programme | Ministry of Agriculture |
| 2. Desert Development Programme | Ministry of Environment and Forests |
| 3. National Watershed Development Project for Rainfed Areas | Ministry of Rural Development |
Which of the pairs given above is/are correctly matched?
- A1 and 2 only
- B3 only
- C1, 2 and 3
- DNone
Show answer and explanation
Correct answer: (d) None
Explanation
The Drought-Prone Areas and Desert Development programmes were run by the Ministry of Rural Development, while the National Watershed Development Project for Rainfed Areas was under the Ministry of Agriculture. None of the pairs is correct.